Project presenter says Evergreen Elementary construction is on track

Aug 17, 2026

Project presenters told the board that footings are poured, prefabrication has started and three contract amendments (validation and two GMPs) are executed; GMP 3 (the guaranteed maximum price covering the full project budget) will be presented at the next board meeting and the team is watching schedule risk closely.

The full story

The Evergreen Elementary construction team told the Enumclaw School District board the project is progressing "extraordinarily well," with footings poured in most areas and early prefabrication under way.