Commissioners shift $90,000 into sheriff's office contract, approve final change orders
Aug 25, 2026
The court approved prime contract change orders and an owner-side transfer of $90,000 into the SCI contract to cover known PCCOs for the Rockwall County sheriff's office remodel; commissioners were told substantial completion is targeted for late September.
The full story
Commissioners approved prime contract change orders 36 and 38 and an official change order that moves $90,000 from the owner's side into the SCI Construction contract to pay for known PCCOs on the sheriff's office remodel.
"We are moving $90,000 into the SCI contract, from the owner side," Commissioner Stacy said, describing allowances and contingency management. He told the court that the transfer funds all known PCCOs and "it doesn't add any additional funds; it just takes funds from one side into the actual contract." The court approved the specific change orders and the official change order in recorded 5-0 votes.
Staff said the owner-side contingency will still show roughly $26,000 after these transfers and that furniture and dispatch consoles are scheduled for the third week of September with substantial completion anticipated by the end of September or early October, subject to contractor scheduling adjustments.
The court also discussed scoping risks for last-phase items and agreed to route any payment and schedule questions to Sal and his team for follow-up before final acceptance.