Copperas Cove ISD construction updates: Fletcher progress, Williams Ledger timelines, athletic fields work ongoing
Nov 18, 2025
Nov 18, 2025
Dr. Schuck told trustees Fletcher Elementary has painting and flooring scheduled (flooring order requires 50% down, 4–6 week lead), Williams Ledger's baseball/softball subbase and drain work are underway, and field netting and rock‑wall elements are being installed; some components are backordered and TASB reimbursements remain delayed.
The full story
Dr. Schuck provided trustees with a construction update on multiple capital projects, including Fletcher Elementary, Williams Ledger Elementary and athletic field work.