Supervisors approve $10,000 amendment for transfer‑station slab engineering

Washington County Board of Supervisors · January 28, 2025

Summary

The board approved a $10,000 amendment to the Lane Group engineering contract to cover additional work on Transfer Station 4’s slab after unforeseen subgrade issues; staff said the firm incurred about $20,000 in extra costs and the reserve balance would remain adequate.

County staff told the board that the Lane Group’s original engineering contract for Transfer Station 4 was $45,500 and that the firm incurred roughly $20,000 in additional engineering costs after discovering unexpected subgrade/soil conditions during work. Staff said no contingency had been built into the contract and requested a $10,000 amendment funded from the reserve for contingencies.

Supervisor McCall moved to approve the $10,000 amendment and authorize the transfer from reserves; the motion was seconded and carried by a seven‑zero vote. County staff and board members discussed whether the engineer had under‑estimated labor and subcontractor time, the policy that professional services under $80,000 can be procured with one quote, and that the reserve balance would remain above $200,000 after the transfer.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source