Supervisors approve $10,000 amendment for transfer‑station slab engineering

Jan 28, 2025

The board approved a $10,000 amendment to the Lane Group engineering contract to cover additional work on Transfer Station 4’s slab after unforeseen subgrade issues; staff said the firm incurred about $20,000 in extra costs and the reserve balance would remain adequate.

The full story

County staff told the board that the Lane Group’s original engineering contract for Transfer Station 4 was $45,500 and that the firm incurred roughly $20,000 in additional engineering costs after discovering unexpected subgrade/soil conditions during work. Staff said no contingency had been built into the contract and requested a $10,000 amendment funded from the reserve for contingencies.