Board okays $10,000 amendment to Lane Group engineering contract for transfer-station slab overage
Jan 28, 2025
The board approved a $10,000 amendment to the Lane Group engineering contract and a $10,000 transfer from contingency after staff reported roughly $20,000 in unforeseen engineering costs tied to subsurface conditions at the transfer-station slab; the vote was unanimous (7-0).
The full story
County staff told the Washington County Board of Supervisors that the Lane Group’s engineering contract for the transfer-station floor-slab replacement was originally $45,500 and that the firm has incurred roughly $20,000 in additional costs related to unexpected subsurface issues encountered during work.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or