Federal shutdown delays push Cape May County bridge permitting and shift project timelines

Apr 28, 2026

County Engineer reported USCG permit processing delays tied to a federal shutdown, moving permit issuance to about Sept. 1 and pushing some construction starts (e.g., a bascule replacement) roughly a year later to September 2027.

The full story

County Engineer Mr. Church updated commissioners on multiple infrastructure schedules, flagging permit processing delays linked to a recent federal shutdown. He said surveys have been completed in some cases but that U.S. Coast Guard permit processing is delayed; for the 96th Street bascule replacement the issuance of a permit is now expected around Sept. 1, which in turn pushes projected construction start dates by approximately one year (estimated construction start September 2027).