Nutter Fort engineering reports Nutter Run finished; Chub Run and Phase II AML projects advance

Jul 28, 2026

Town engineers reported the Nutter Run project is complete pending testing, the Chub Run sewer work is progressing with a contractor time extension to sync with a new wastewater plant, and Phase II AML pre-bid and bid dates were set for Aug. 20 and Sept. 8 (possibly Sept. 10).

The full story

Town engineering staff told the council that the Nutter Run project is complete but will be placed in service only after samples taken Thursday return acceptable results. The council was informed that Chub Run sewer work is progressing well; project timing is interdependent with the new wastewater treatment plant across the interstate, so the contractor is being granted a time extension to align activations.