Castleberry High School bond project 40% complete, program manager says

Castleberry ISD Board of Trustees · November 11, 2025

Summary

Bond program manager Cameron Holloman told the board the Castleberry High School bond project is about 40% complete, with stormwater connections and major renovation milestones achieved; he said the team expects to be 'dried in by February 1.'

Cameron Holloman, the district’s bond program manager, presented the '24 CHS bond construction update and told trustees the project is roughly 40% complete and about 30% paid. He highlighted infrastructure milestones — stormwater connections and underground work completed — and renovation progress including the band hall, roofing and interior sheetrock. "So just briefly, we're about 40% through the project. We've paid about 30% out now," Holloman said.

Holloman showed photos of completed exterior windows, moisture barriers, and areas prepared for structural steel and mechanical systems. He said the team expects to be dried in by February 1 and to continue monitoring budget and schedule while seeking opportunities to save soft costs while subs are on site.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source