Facilities estimates: compressor $55,000, chiller $175,000; board told to factor into bonding plans
Jun 9, 2026
Jun 9, 2026
Tyson Benner told the board an HVAC compressor replacement would cost about $55,000 and a new chiller about $175,000 and recommended the board factor those expenses into any bond proposal.
The full story
At the June 9 meeting, Tyson Benner provided cost estimates for facility repairs: about $55,000 to replace a compressor and approximately $175,000 for a new chiller. He suggested that if the county proceeds with a bond, those items should be included in the calculations.