Facilities estimates: compressor $55,000, chiller $175,000; board told to factor into bonding plans

Jun 9, 2026

Tyson Benner told the board an HVAC compressor replacement would cost about $55,000 and a new chiller about $175,000 and recommended the board factor those expenses into any bond proposal.

The full story

At the June 9 meeting, Tyson Benner provided cost estimates for facility repairs: about $55,000 to replace a compressor and approximately $175,000 for a new chiller. He suggested that if the county proceeds with a bond, those items should be included in the calculations.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in