Pool project 55–60% complete; gutter delay could shift completion slightly
Mar 3, 2025
DPW reported the community pool is about 55–60% complete; most concrete work is done but the gutter manufacturer delayed delivery, which could push completion by up to two weeks. Project remains under 5% in change‑order costs and the contractor is targeting Memorial Day operational readiness.
The full story
Anthony Carr gave a construction update on the village pool, saying the project is roughly 55–60% complete by dollar value and work in the pools (concrete and piping) is largely in place. He said pool filter building finishes, piping, and many site utilities remain and that the DOH inspections passed so far.