Staff reported the Cure-In-Place Piping project's contingency balance is $67,544 and said engineers are determining which additional pipe sections to include; collapsed sections will require excavation rather than lining.

The full story

Commissioners were updated on the Cure-In-Place Piping (CIPP) project. Cherek reported the contingency for the CIPP project sits at $67,544 at the time of the meeting. Engineers from Vierbicher and project staff are reviewing possible additional sections to include in the lining work; the minutes note that some pipeline sections will need excavation because of pipe collapse and therefore cannot be completed with lining alone.