Council hears Pine Street sewer replacement plan; engineer estimate $893,000
Jun 11, 2026
Jun 11, 2026
Sewer Supervisor Don Erickson outlined a Pine Street sanitary sewer replacement project using pipe-bursting and open-cut methods, citing an engineer's estimate of approximately $893,000 and a mid-June bid opening with construction anticipated later this summer if a bid award is approved.
The full story
Sewer Supervisor Don Erickson presented the Pine Street Sanitary Sewer Replacement Project to the council on June 11, describing both pipe-bursting and conventional open-cut construction methods intended to replace aging sewer infrastructure and reduce groundwater infiltration.