Designers and contractors told the committee that calculations for the attic dry sprinkler system did not show sufficient PSI margin; they identified four potential solution avenues, including flow tests with adjacent city projects, and warned that adding heat or system changes could delay parts of the project.
The full story
Contractors reported that modeling for the attic dry sprinkler system in the 1892 attic did not achieve an adequate pressure margin. A presenter said the design team identified four possible solution paths and that some solutions depend on flow tests and data from adjacent city projects. "When we modeled the system... we're not, to your point, achieving the... safety margin for the PSI," Kyle Osmek said, adding the design team is pursuing options and that the project team expects more information in the next two weeks.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →