CCISD bond projects nearly complete; district reports about 88% finished
Summary
Superintendent Evan Cardwell and Maintenance Director Joe Hernandez reported that CCISD's 2023 bond projects — including Ag barn, canopies, gym work, parking lots, HVAC and cameras — are approximately 88% complete.
Superintendent Evan Cardwell and Maintenance Director Joe Hernandez updated trustees on the progress of the district's 2023 bond projects at the Feb. 23 meeting.
The report covered multiple campus projects: the Ag barn; Calhoun High School bus lane canopy and gym II metal siding and gutters; the Calhoun High baseball-field parking lot; Hope High School front and back parking lots and the HJM back parking lot; Seadrift School and JR Elementary School gym window infills and gym siding; Seadrift School main building and dressing room roof; Calhoun High School baseball and softball batting cages; HVAC work at the district support center; and campus camera systems. The district estimated the 2023 bond work is approximately 88% complete.
Trustees received the update; no action was required at the meeting, and administration will continue oversight and report on remaining work and timelines.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.