County Engineer Mr. Church reported the Seashore Road paving schedule, ongoing Roosevelt Boulevard work, resumption plans for Fishing Creek Road after pipe delivery, and an April 28 consultant presentation on Corson's and Townsend's Inlet Bridges.

The full story

County Engineer Mr. Church briefed the Board on active and upcoming road and bridge work. He said base paving on Seashore Road is scheduled to begin Monday, March 30, with the surface course to start the week of April 8 and anticipated completion by the third week of April. Roosevelt Boulevard work remains underway with roughly three weeks of work before base paving resumes and the concrete barrier can be removed to restore normal traffic patterns.