Engineering reports progress on AMD projects, ROWs and Chub Run; vendor bid opening delayed
Feb 24, 2026
Feb 24, 2026
Engineering reported Phase 1 and Phase 2 AMD work with ROW acquisition nearly complete (30 of 34) and a DOH permit under review; Chub Run vendor bid opening was moved to March 10, 2026, and Phase IV awaits contractor remobilization.
The full story
Engineering staff presented multiple infrastructure updates. For Phase 2 AMD, 30 of 34 right-of-way acquisitions are complete; town staff are still seeking ROWs from two businesses, one utility and one resident, and a Department of Health permit is under review. A to-bid meeting with AML was scheduled and tree felling was discussed as part of preparatory work.