County engineer reports paving, bridge work and seal-coating schedule
Jul 9, 2026
Henry County Engineer Scott Stephenson told the Transportation Committee on July 9 that crews finished asphalt paving in Annawan and Geneseo, township seal coating began July 6 with completion expected mid–late August, and bridge work in Kewanee and Cambridge is moving forward; he also noted he will be on vacation starting July 16.
The full story
Scott Stephenson, Henry County engineer, reported to the Transportation Committee on July 9 that crews have completed asphalt paving projects in the Village of Annawan and the City of Geneseo and that township seal coating began July 6 and is scheduled to finish in mid to late August.