Animal control building: foundation expected mid‑June; delivery set for July 6

Jun 8, 2026

Chief Sheriff Tipsword said the Menssen Trust Agreement is filed, septic permit is pending, foundation work should begin about June 16 and the building delivery is scheduled for July 6; the committee discussed related roofing reuse separately.

The full story

Chief Sheriff Tipsword told the committee the Menssen Trust Agreement for the animal control building has been signed and is on file with the county clerk. He said the septic contractor located dirt and will start hauling it to the site, the Health Department septic permit was expected this week, the foundation should begin around June 16, and the building is scheduled to be delivered July 6.