Board approves $3,500 proposal to widen E3 Basin control structure to improve outflow

Mar 24, 2026

MRI Construction Proposal #606 was approved to widen the E3 Basin control-structure opening to maximum allowable width for improved drainage; the board requested before-and-after photos and asked about the possibility of adding a manual gate near the structure.

The full story

Mrs. Adams presented MRI Construction Proposal #606 to widen the opening on the E3 Basin control structure. Mr. Krebs explained the work would use a concrete saw to widen the weir to the maximum allowed to increase outflow toward the FPL easement and discussed whether a manual open/close gate could be installed.