Core sampling revealed insufficient base layers on several streets, prompting full reconstructions and the inclusion of curb replacement costs previously unbudgeted; committee proposed requiring preliminary core samples for future projects.

The full story

During the Feb. 18 meeting, committee members reported that initial estimates relying on milling and overlay proved inadequate after core samples showed insufficient base material in multiple locations. As a result, some sections originally planned for an overlay must be rebuilt, increasing costs and prompting the removal of certain streets from the base bid to preserve contingency funds.