Wastewater plant work advances: clarifiers, basins and solids building progress reported
Sep 9, 2025
Project contractor continues headworks and clarifier installations, completed demolition in the solids-handling building and advanced grading and drainage works; staff said recent work included leak testing, electrical installations, and preparation for yard lighting.
The full story
Brian Moss gave a detailed update on the wastewater treatment plant improvements, describing steady progress across multiple components. Moss said headworks and equalization basin work are underway with leak testing, motors and gearboxes installed on clarifiers, Landia mixers in place, and the solids-handling building demolition mostly complete with new concrete pads being prepared for equipment installation.