Engineer recommends full authorization for Highway 61 utilities design after revised cost estimate

Dec 9, 2024

City Engineer told the committee the Highway 61 utilities improvement estimate fell to about $7.227 million from a prior $9.1 million after correcting a double‑counted item and asked for authorization of $140,000 for preliminary engineering and $530,000 for final design so work can proceed with MnDOT's schedule.

The full story

The City Engineer presented updated estimates and a design authorization request for sanitary sewer and water improvements tied to the Highway 61 project.