Engineer: county contractor left temporary pavement on 5th Street; final paving planned next spring

Nov 25, 2024

A council member raised safety concerns about an unfinished 5th Street intersection. The city engineer said the county contractor ran out of time this season and installed temporary pavement for winter; final paving and added signage are planned for next spring.

The full story

A council member asked about the condition of 5th Street, noting a substantial drop in pavement level near 6th Avenue and a section that appeared unfinished. The city engineer said the county contractor ran out of time this season and completed storm sewer, water main and curb work but was unable to finalize pavement across the intersection.