WWTF Operator Edward Tracey reported the wastewater treatment facility 'continues to perform without incident' and said there is reserve capacity to accommodate a sewer allocation increase for Robco Trucking at 318 VT Route 22A; the zoning permit depends on updating the wastewater permit and Select Board action on user fees.
The full story
At the Feb. 9 meeting, the board reviewed a sewer allocation increase request submitted by Elias Erwin of Landmark Engineering on behalf of Robco Trucking for property at 318 VT Route 22A.