Director of Schools reports progress at multiple school athletic sites

Jan 6, 2025

Director of Schools Scott Langford reported progress on stadium and field projects across Sumner County schools: BHS grading ~60% complete, parking 85% graded, drainage 90% complete; field lights installed and footers for structures planned when weather and utility work allow.

The full story

Director of Schools Scott Langford provided an athletic facilities update to the Education Committee, reporting construction progress at multiple schools. "Bulk grading on top of the hill is about 60% complete," the report states for BHS; parking behind the visitor side is about 85% graded and drainage and the detention pond are roughly 90% complete. New field lights have been installed and crews will begin footings for the concession and restroom building when weather allows.