Board approves WWTP payment requests and three-year generator maintenance agreement
May 18, 2026
May 18, 2026
The board approved payment requests for the WWTP project totaling $27,334.45 (SD Ellenbecker $15,050; August Winters & Sons $12,284.45) pending required approvals, and approved a three-year generator maintenance agreement for $2,356.86.
The full story
The board approved a payment request from SD Ellenbecker for $15,050 for the WWTP sodimate enclosure, contingent on approval from MSA and the DNR. Trustees also approved payment request #8 from August Winters & Sons for $12,284.45 related to the WWTP project.