State rescinds drainage funding; Clinton sidewalk extra-work request cut to $44,860

Feb 18, 2026

Clinton officials said final sidewalk design work is underway along Route 1. After the State DOT rescinded an offer to fund 80% of planned drainage work, the town’s extra cost dropped; the revised extra-work request is $44,860 and the town’s share is $8,972.

The full story

Clinton’s Town Council was told on Feb. 18 that final design work is underway for a sidewalk project extending west from downtown along Route 1, but one previously planned drainage element will not proceed after the State Department of Transportation rescinded an earlier funding offer.