Council Approves $154,121.38 Change Order; Intersection Project Tops $3.32 Million
Sep 12, 2024
ARRO Consulting told council the negotiated Final Change Order for the intersection project is $154,121.38, bringing the final project price to $3,322,687.08; council approved the change order 6–0.
The full story
Brad Smith of ARRO Consulting reported that negotiations with CMS concluded and presented a Final Change Order in the amount of $154,121.38 for the borough's intersection project. Smith stated the "final price of the intersection project was $3,322,687.08." Robert Metzgar moved to approve the change order; Lisa Gantner seconded and the council recorded the vote AYES 6, NAYS 0, ABSENT 1.