Quotes to replace mercury switches in pump house controllers were discussed; the Board deferred purchase pending results of an upcoming well pump inspection and heard that full SCADA integration for water sites could add $25,000–$50,000 per site.

The full story

Director of Public Works Keith Leitzinger presented two quotes for replacing mercury switches in pump house controllers: a basic replacement (B&M Electric) and a SCADA-ready option (Pilling). Engineer Jordan Fure told the board that adding full SCADA capability to water system sites could cost an additional $25,000–$50,000 per site.