Board reviews long-range plan: backup well, gatehouse and monument cost updates

Apr 28, 2026

The Board reviewed a revised Long Range Plan with updates including a near-complete backup irrigation well ($291,500), traffic calming costs ($26,739), monument replacement estimates ($250,000) and gatehouse renovation cost projections for FY2026–27.

The full story

Eric Long distributed and reviewed a revised Long Range Plan, reporting that the Traffic Calming Project was completed at a cost of $26,739 and that a Backup Irrigation Well project is near completion with an estimated cost of $291,500. Long said the new well is expected to become the district’s primary well after installation and water-quality testing; the existing well would remain as a secondary well due to a kink in its casing.