Board reviews 640‑acre cap and 250‑foot setbacks in draft data‑center rules
Aug 18, 2026
Staff proposed a 640‑acre cap on cumulative development area and changed setbacks so principal buildings and standalone mechanical yards are 250 feet from project boundaries; board members asked clarifying questions about screening and maximum building heights.
The full story
During a redline walkthrough of Resolution PC 26‑2, planning staff said the draft would limit the cumulative development area "for all phases, components, expansions, and related improvements shall not exceed 640 acres." (staff comment summarizing the new limit.)
Staff explained the limit is intended to prevent sprawl and avoid applicants structuring projects to evade the cap. The rules define which areas are excluded from the development area calculation and require the 640 acres to be contiguous.
The draft also standardizes setbacks: staff described that standalone mechanical yards and substations would have a 250‑foot setback from the project boundary and that principal buildings were changed from a 200‑foot to a 250‑foot setback to match mechanical yards. The board discussed screening requirements; one member noted maximum building height figures and asked whether mechanical equipment could be screened to achieve a functional height reduction.
Board members asked follow‑up technical questions about how the setback rules would be applied and how screening and maximum height would be measured; staff pointed to the new building‑height definition and related screening options in the draft.