Two inactive solar special-exception permits flagged as void after multi-year inactivity

Jun 10, 2026

Staff told the Caroline County Board that two previously approved solar special exceptions (Muskegee Solar SPX 07-2021 and Shad Solar SPX 08-2021) appear to be void under county zoning for failing to commence construction; the board accepted staff's recommendation and deferred formal determinations to the zoning administrator.

The full story

County planning staff told the board that Muskegee Solar LLC's special-exception permit (SPX 07-2021), approved June 14, 2022 for a 4.9-megawatt project on Balti Road, has not commenced construction and that the permit is therefore void under county zoning provisions that terminate special exceptions that are not acted upon within the required timeframe. Staff said a permit-by-rule was applied for at the state level but no local construction activity or site-plan approvals have occurred; the permit’s automatic voiding stems from the county code provision applied to special exceptions.