Engineer reports progress on sewer and corridor projects; multiple design milestones scheduled
Summary
Town engineers updated council on Phase IV sewer budget items, LifePoint sewer hold status and CWSRF submission, Route 20 corridor contractor timing for June 2025, and Phase I/II AMD design and NEPA milestones through April 2025.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town engineers gave a multi-part report covering sewer and corridor projects. For Phase IV sewer, the minutes list $104,818.22 remaining for an additive alternate at Sandy’s Hardware, note a need for right-of-way acquisitions and a pending PSC case, and record contractor quotes of $132,000 and $172,000 for an unspecified line item. The LifePoint sewer item is on hold; a CWSRF IUP form has been submitted.
The Route 20 corridor contractor plans to start work in June 2025 and the engineer indicated a change order will likely be needed to account for a winter shutdown. For Phase II AMD work, the NEPA environmental assessment was updated and awaits U.S. Fish and Wildlife Service correspondence for OSM approval; design milestones include a 60% submission on 3/21/2025, 90% design later in April and a final design target of 4/30/2025. The minutes also note mailers to residents and WVDOH coordination as next steps.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.