CDD says drainage work nearly complete; crews to remove and replace trees, contingency to cover unexpected repairs
Jun 23, 2026
District engineer reported four drainage sites under construction with pipe/grade work complete in Turnberry, Palmetto Dunes nearing completion, and Oak Run work beginning week of June 29; staff logged additional costs (environmental review and an unexpected A/C coolant‑line repair) to be charged to Contingency.
The full story
District Engineer Charlie Krebs told the Board that all four drainage improvement sites are under active construction: sites are cleared, silt fences installed, fill staged at Turnberry, pipes installed and grading completed in Turnberry, and Palmetto Dunes expected to be completed by the end of the week.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →