Pumping station project running behind; council tables $80,430 inspection amendment pending USDA documentation

Nov 5, 2025

GMB reported the pumping station project likely will miss its Nov. 29, 2025 substantial completion date and shift to January 2026; GMB requested an amendment up to $80,430 for full‑time inspection services allegedly required by USDA, which the Council tabled pending written USDA documentation.

The full story

Engineers Jason Lytle and Andrew Lynch of GMB told the council that the pumping station project — originally scheduled for substantial completion on Nov. 29, 2025 with 30 days to final completion — is running behind schedule and now looks likely to finish in January 2026. The project delay prompted a request from GMB to amend the owner–engineer agreement to add full‑time inspection services.