Commission hears update on Trip 2 engineering and potential ALDOT project overruns
Apr 9, 2026
County roads staff told commissioners they received a proposed $268,000 engineering agreement for a Trip 2 project and said a bridge/culvert project has change orders that could add roughly $300,000–$350,000 in overruns; the state covers its contract share, and the county would be responsible for a portion of overruns.
The full story
Roads staff briefed the commission on multiple projects, including a proposed agreement with GMC Inc. to provide engineering for a Trip 2 project near Coosa Valley Elementary with a local share estimated at $268,000.