Select Board approves three DPW change orders, including Bishop Road and Right Way projects

Sep 1, 2026

The board approved DPW change orders for Bishop Road water-main extension, Mill Street drainage improvements and Right Way sewer pump-station upgrades; the Bishop Road change-order amount discussed in the presentation and the motion differ in the transcript and should be verified.

The full story

Dan Hennepin, public works director, presented three final or supplemental change orders and requested signature authority for the chair. He said the Bishop Road water-main extension required additional drainage and fittings, extending the contract time by 60 days and recommending a change order; in the presentation the amount was given as $128,890 but the motion recorded a different figure ($28,890). The board approved the change order for signature by the chair.