Applicant’s engineer testified that DPZ treats >30% critical root‑zone disturbance as effectively killing a tree; engineers said the required stormwater pond and easements could not be sited without disturbing specimen trees and the 75‑foot stream buffer.

The full story

At the hearing the applicant’s civil engineer explained why the proposed subdivision layout required disturbance of the stream buffer and removal of several specimen trees. Under cross‑examination the engineer clarified the technical basis for the applicant’s waiver requests and the limits placed by the county’s forest conservation manual.