County Engineer reports flood-related damage and project schedules; shouldering paused
Jul 28, 2026
Jul 28, 2026
Floyd County Engineer Adam Miller reported shouldering work on B60 is paused after local flooding; a culvert on 140th Street washed out and remains closed. He updated timelines for the HDP(117) 155th Street Bridge (November letting), 170th Street bridge replacement, and Packard Avenue resurfacing (late August/early September).
The full story
County Engineer Adam Miller told the Board that recent heavy rains and flooding along the Cedar and Little Cedar Rivers forced a temporary pause in shouldering work on B60, though crews expect to resume next week.