Silvercrest seismic retrofit: scope, timeline and procurement explained

Oct 18, 2024

ZCS Engineering presented the planned Silvercrest Elementary seismic retrofit scope (library/music building), explained CMGC advantages for cost and schedule control, and outlined an RFP timeline leading to a December recommendation and year‑end award.

The full story

Kevin Hassett of ZCS Engineering told the board the work will focus on Silvercrest Elementary's library and music building and that ZCS is the structural and architectural consultant on the project. He explained the CMGC procurement method, saying it emphasizes qualifications and early contractor involvement rather than low bid: "The construction manager, general contractor, CMGC, method, basically, you hire the contractor based off of qualifications," Hassett said.