Interstate Engineering presented a plan for the Schick Bridge replacement (BRJ-0019(027)), proposing a bid date of Aug. 7, 2026, substantial completion by Nov. 15, and final completion Dec. 1, 2026; the county will apply for cost share on construction engineering.
The full story
Maria Tomac of Interstate Engineering presented the Schick Bridge replacement project BRJ-0019(027) on June 17 and proposed a timeline that sets a bid date of Aug. 7, 2026; a substantial completion date of Nov. 15, 2026; and a final completion date of Dec. 1, 2026. Tomac told the board the county will apply for cost share on construction engineering for the project.