River Ridge Board awards $1.11 million drainage contract to Clark Construction

Apr 28, 2026

The River Ridge CDD approved a not‑to‑exceed $1,111,860 contract with The Clark Construction Group Inc. to complete four stormwater management phases, including a 5% additional contingency; an optional Oak Run HOA connection was priced at $197,201.47.

The full story

The River Ridge Community Development District Board on April 28 approved The Clark Construction Group, Inc.'s bid to complete four stormwater management phases — Oak Run, Turnberry, Palmetto Dunes and Seaside IV — under a not‑to‑exceed contract of $1,111,860, including an additional 5% contingency.