ASD administrators tell board Abbott Loop could be demolished using remaining bond funds
Aug 27, 2026
Administrators said roughly $4 million remains from a prior bond that could pay for Abbott Loop demolition if the board approves; they warned of PCBs and said demo timing depends on bids and procurement lead times.
The full story
District administrators told the board that, if approved by the board, the remaining prior‑year bond balance (about $4,000,000) could be used to pay for Abbott Loop demolition and that procurement timelines make spring demolition the realistic window.