Engineer reports bridge and culvert projects; board signs updated 28E maintenance agreement

Aug 5, 2026

County Engineer Nick Kauffman updated the board on road and bridge projects and the Board approved the final pay estimate for the W9 Lincoln RCB Culvert Project and an updated 28E maintenance agreement increasing the per-mile bridge/culvert cost allocation from $500 to $10,000.

The full story

County Engineer Nick Kauffman provided an update on Secondary Roads projects, reporting that Grimes Asphalt is expected to begin work on the Casey project next week and Govco is anticipated to receive bridge beams for the W18 bridge project. Design work is ongoing for the N8 Richland and Eureka box culvert projects, and plans for the W9 Washington project have been posted for letting.