Molalla River bond project moves into construction after December permit approval

Jan 27, 2026

Consultants told the Bond Oversight Committee the district received a building permit in December and construction is underway: footings are poured and initial plumbing inspected; right-of-way work is planned for late spring or early summer ahead of a planned September 2027 school opening.

The full story

The Molalla River School District’s bond project has moved into active construction after the district received a building permit in December, consultants told the Bond Oversight Committee on Jan. 27.