County engineer reports progress at Progress Park, Barrett Mill Road and Foster Falls solar site

Mar 5, 2026

County Engineer Mr. Kinser updated commissioners on Progress Park road and cul-de-sac work, Barrett Mill Road water-line progress and leak repairs, and stabilization and permit conditions at the Foster Falls solar project (lighting, transformers, and battery-system permitting were discussed).

The full story

County Engineer Mr. Kinser walked the commission through several ongoing public-works and private development sites. He reported the cul-de-sac and connecting road work in Progress Park is nearing inspection and stabilization, the railroad ties at the park had been replaced, and that VDOT’s road-connection work is progressing and expected to continue into next year.