Board hears progress on Mills Pond, Atlas 14 and SSES manhole projects; approves SSES pay request
Aug 18, 2026
Consor reported the Mills Pond regulatory improvements project is ahead of schedule and near substantial completion; the Board approved Pay Request No. 2 for the SSES Manhole Rehabilitation Project ($78,247.53) and asked staff to meet with RJN about stormwater concerns.
The full story
Consor engineer John Millsap told the Board Aug. 18 that the Mills Pond Regulatory Improvements Project is ahead of schedule and should be substantially complete within a couple of weeks. He presented Contractor’s Application and Certificate for Payment No. 6 for the Mills Pond project in the amount of $66,957.84; the Board approved that payment unanimously.
Millsap also discussed the SSES Manhole Rehabilitation Project, Phase 1. RJN Group submitted correspondence flagging stormwater regulatory concerns — including contractor concrete wash-out protocols and accumulated trash at the staging site — and recommended attention to those issues. The Board approved RJN’s Pay Request No. 2 for $78,247.53 and asked staff to schedule a follow-up meeting with RJN to address the flagged stormwater concerns.
The Board’s approvals were unanimous and recorded as motions.