Garlic Creek, Onion Creek trail projects updated; change orders and completion targets set

Mar 26, 2025

Staff reported progress on bond-funded trail work: 800 linear feet complete on Garlic Creek Trail with a $70,000 deduct for a natural bridge finish and a new completion date of April 20, 2025; Onion Creek Trail has 1,400 feet poured and a $28,660 change order for a retaining wall and manhole work.

The full story

Parks staff reported progress on two bond-funded trail projects during the March 26 commission meeting. Garlic Creek Trail has roughly 800 linear feet completed; staff said a change order deducting $70,000 was approved to specify a naturally weathered bridge finish instead of painted structural material, and staff added 30 days to the contract, putting substantial completion at April 20, 2025.