Garlic Creek, Onion Creek trail projects updated; change orders and completion targets set
Mar 26, 2025
Staff reported progress on bond-funded trail work: 800 linear feet complete on Garlic Creek Trail with a $70,000 deduct for a natural bridge finish and a new completion date of April 20, 2025; Onion Creek Trail has 1,400 feet poured and a $28,660 change order for a retaining wall and manhole work.
The full story
Parks staff reported progress on two bond-funded trail projects during the March 26 commission meeting. Garlic Creek Trail has roughly 800 linear feet completed; staff said a change order deducting $70,000 was approved to specify a naturally weathered bridge finish instead of painted structural material, and staff added 30 days to the contract, putting substantial completion at April 20, 2025.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →