County engineer outlines Bridge 142, Bridge 58 and overlay work; Sept. 11 target for an overlay opening

Sep 1, 2026

County engineer Nate described bridge repairs—including mud-wall removal, bearing-pad work, hydro-demolition and a wearing-surface overlay—and said Bridge 142 has a 75-day contractor schedule while a local overlay project aims for a Sept. 11 reopening.

The full story

County engineer Nate gave commissioners a detailed update on three bridge projects. He said crews removed a portion of a mud wall at Bridge 142, replaced bearing pads, and plan hydro-demolition and an overlay to address scour on the deck; under the contract the contractor has 75 days to complete the work.